Environmental
Information Document
(EID)
The EID process will be addressed on a case
by case basis by EPA. Appendix
C (43 K PDF)
of the Arizona NPDES General Permit for CAFOs lists the information
required for an EID. The producer will need to communicate directly
with various agencies or otherwise conduct his/her own research
to gather the information required.
The reason for requiring an EID for new CAFOs
is so that EPA can adhere to the requirement that "new source" NPDES
permittees must be subject to a National Environmental Policy Act
(NEPA) review, as required by 40CFR 122.29(c). Through the EID process
explained in and required by Parts II.C and II.D of the general
permit (Additional Information Regarding New CAFOs and Commencement
of Authorization to Discharge), EPA hopes to streamline the NEPA
process for "new sources," by enabling them to obtain coverage under
the statewide general permit rather than have to apply for an individual
NPDES permit. The NEPA process requires that EPA address all stated
environmental concerns and mitigate any significant adverse impacts,
if necessary.
It is difficult to predict the process. However,
a best case scenario and a more problematic scenario are presented
here. The best case scenario is that EPA receives the EID and issues
an Environmental Assessment (EA) and a tentative Finding of No Significant
Impact (FNSI). Then the EA/FNSI is posted in a local newspaper to
allow the public 30 days to comment. After 30 days, if no comments
are received, EPA can issue a final FNSI and the operator obtains
coverage under the NPDES general permit within 90 days of having
submitted his/her NOI and EID.
A more problematic and time-consuming scenario
may also occur following submittal of the EID to EPA. Due to a significant
impact from the facility (e.g. an endangered species or its critical
habitat is adversely effected), EPA could develop an EA/FNSI, following
consultation with the applicant/operator, that states there are
impacts which will be mitigated to a less than "significant" level
and that the operation will be covered under the NPDES general permit.
However, if public comment is strongly against this outcome, it
may lead EPA to conclude that "significant" adverse impacts remain
likely. (EPA could also reach this conclusion independently, without
proceeding with an EA/FNSI and opportunity for public comment.)
Whether or not public concern or objections
could change the FNSI to a finding of significant impact is unclear.
EPA makes the final determination on whether or not there is a significant
impact. However, enough public comment may change the EA. There
is little clarity on what exactly constitutes a significant impact.
The National Environmental Policy Act (NEPA) that requires the process
does not define what significant impact means. However, EPA has
general guidance concerning what kinds of impacts may or may not
be considered "significant." This guidance may be obtained from
EPA Region 9's Federal Activities Office at (415) 972-3850.
If significant impact is found, the impact
must be mitigated to less than significant impact for approval of
the project (in this case, coverage by the permit).
Once there is a finding of significant impact,
an Environmental Impact Statement (EIS) is required. This will be
a long process that requires very detailed information about the
potential impacts to the environment. Completing this process requires
development of a Draft EIS that is subject to public notice and
comment and a Final EIS which addresses all public concerns and
mitigates all identified "significant" impacts to a less-than-significant
level.
It is possible that the NPDES general permit
would not be approved for an operation because of significant impact(s).
In that case, the producer would need to get an individual permit
to be covered. The individual permit would need to go through a
public comment process as well. If a producer foresees problems
with getting the general permit, s/he can submit the EID and the
draft individual permit at the same time so that s/he is only required
to have one public notice period. Coverage under the general NPDES
permit or issuance of an individual NPDES permit, can only occur
after the NEPA process has been completed.
The EID and the Notice
of Intent (NOI) to be covered by the permit are due at least
90 days prior to beginning operation of the CAFO. EPA suggests that
operators allow additional time for the EID process in order to
allow more time to mitigate any issues that come under public scrutiny.
Throughout this process, EPA cannot prevent
a producer from building or operating on the location. However,
EPA recommends that the NEPA process be undertaken prior to construction,
in order that substantial retrofits or modifications to the project
not be required after-the-fact. There reason for this is that there
is a possibility that the NEPA environmental review process might
identify significant adverse impacts which must be mitigated or
addressed by fundamental changes to the proposed project in order
for the CAFO to obtain general or individual NPDES permit coverage.
You can look at the NPDES Permit Writer's
Manual, Chapter 4 for information on the application process. Go
to Permit
Issuance Process Policy and Guidance Documents and look about
half-way down the page for the manual. The publications are listed
alphabetically. Keep in mind, the NPDES program covers all "point
source" pollution sources, including heavy industry and waste water
treatment plants. Therefore, some of what is in the chapter 4 does
not apply to CAFOs.
For an individual permit, producers need to
complete Forms 1 and 2B. (see Permit
Issuance Process Policy and Guidance Documents).
If a producer does not submit an EID and either
an NOI for the general permit or an application for the individual
permit prior to starting the new operation operation, s/he can do
so later. However, s/he will still be required to submit an EID
under the current, five-year permit.
EPA's new contact concerning all issues related
to general or individual NPDES permits for Arizona CAFOs is Jenny
Mann, whose number is 415-972-3512. Jack Landy and Shirin Tolle
no longer work at EPA.
Page updated 7/02
|